January 2016-January 2018: Phase 1New construction in South parking lot, classes in existing buildingsJanuary 2018-June 2018: Phase 2Renovations and additions to old portions of South building, classes in new portions South building and old North buildingJune 2018-July 2019: Phase 3Demolition and new construction at North building, classes are phased into completed, new High SchoolSummer 2019Project completion