• Current Project Timeline: Key Dates 

    January 2016-January 2018: Phase 1
    New construction in South parking lot, classes in existing buildings
     
    January 2018-June 2018: Phase 2
    Renovations and additions to old portions of South building, classes in new portions South building and old North building
     
    June 2018-July 2019: Phase 3
    Demolition and new construction at North building, classes are phased into completed, new High School
     
    Summer 2019
    Project completion
     