- Physical Plant and Facilities
- State High Project Blog
State High Project Blog
-
Notes: Administrative update of September 26
Posted by EDWARD POPRIK on 9/27/2016Trailer News:-
The positive is that the electric and safety items all passed
-
Only item not to pass is insulation
-
Inspection is scheduled for Wednesday (stay tuned)
-
Cleaning of trailers will continue this weekI am looking forward to having the trailers in our rearview mirror.
General News:-
Concrete pours for slab on deck will occur this Wednesday and Thursday in Pods “A” and “D”
-
Transition from underground utilities in connector area (outside of library and science rooms) continues
-
Electrical Conduit continues to be laid and cement poured over
-
Rock hammering will continue as more rock is in the way of the conduit installation
-
-
Notes: Administrative update of September 6
Posted by EDWARD POPRIK on 9/6/2016South News:-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/19
-
Work closest to the South Library (if you haven’t been to the South library to take a look, it is worth your time)
-
Concrete retaining wall is for the main mechanical wall
-
On top of that wall will be the floor of the new gym (hard to believe)
- Area to the right of that will be the student success lab, roar store, cafe, and counseling office
- Area beyond the wall will be classrooms and the media center (library)
North News:-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/12
General News:-
Project continues on schedule with similar work on foundations, masonry, mechanical rough-ins, steel work… many workers are on site
-
-
Traffic flow and parking for the 2016-2017 school year
Posted by EDWARD POPRIK on 8/18/2016This will be the flow for the first day of school, scroll down for the traffic flow until 8/29
Student drop-off is via the Logan Ave. entrance.
-
Notes: Administrative Update - August 15
Posted by EDWARD POPRIK on 8/17/2016South News:- work continues on the 4 pods and progress is seen daily
- demolition work on lower parts of the South has occurred and utility work continues
- back lot and exit lane will be paved tomorrow (weather permitting)
- parking lot line striping will take place some time late this week or early next week (weather permitting)
- Modular classrooms:
- working on finishing touches of interior and installation
- looking to finish cleaning and move furniture in through next weekend
- waiting on West Penn Power to arrive and connect electric and installation of ramps
- as CJ’s email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
- we were in the trailers this week and they are going to be very nice, comfortable spaces when complete
North News:- Modular classrooms: (same as South)
- working on finishing touches of interior and installation
- looking to finish cleaning and move furniture in through next weekend
- waiting on West Penn Power to arrive and connect electric and installation of ramps
- as CJ’s email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
General News:- overall work is still on schedule despite the rainy weather as of late
-
June 30 - 1,107 days to completion
Posted by EDWARD POPRIK on 6/30/2016The project continues to be on schedule!
With the weather forecast and current staffing by the contractors, everything looks great for a productive summer. The footprint for each of the 4 educational units along Westerly Parkway is complete. Masonry continues to advance.
-
June 1 - 1,136 days to completion
Posted by EDWARD POPRIK on 6/1/2016Unit D: Final grading is finishing and foundations have begun.
-
May 26 - 1,1,42 days to completion
Posted by EDWARD POPRIK on 5/25/2016
Unit B: Masonry continues.The project is on schedule and there are no out of the ordinary issues at this point.
-
Notes from the May 23 meeting
Posted by EDWARD POPRIK on 5/23/2016South News:-
Forklift slid in the mud against the fencing near Welch. Repair has begun.
-
MDF room is near completion and we will be moving server racks and equipment into the room this week (outside Pickering Plaza to outside the Auditorium South)
-
Everything is still on schedule
-
foundation pouring
-
retaining wall near existing South auditorium
North News:-
Data Center work continues
-
Restricted access to the rear continues (unchanged)
General News:-
June 1st- Air Quality tests will be conducted in both the North and South buildings
-
Thursday is the elementary tree planting ceremony at 3:45 on Community Field
Future News Items-
For your planning, the absolute “No Access to the South Building” date is scheduled for Wednesday, June 15th.
-
-
May 20 - 1,148 days to completion
Posted by EDWARD POPRIK on 5/20/2016Progress pictures from May 20: