June 1 - 1,136 days to completion

Posted by EDWARD POPRIK on 6/1/2016

 
Good progress again this week and everything is on schedule.

Unit A: Foundation  and slab work continues, Masons are working and have begun setting the garage door frames.

Unit B: Elevator shaft is being poured, we have begun discussions on the remaining items needed to allow work to commence on the second floor.

Unit C: Masonry and slab installations continue.

Unit D: Final grading is finishing and foundations have begun.

 