Notes: Administrative update of September 6
Posted by EDWARD POPRIK on 9/6/2016
South News:
-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/19
-
Work closest to the South Library (if you haven’t been to the South library to take a look, it is worth your time)
-
Concrete retaining wall is for the main mechanical wall
-
On top of that wall will be the floor of the new gym (hard to believe)
- Area to the right of that will be the student success lab, roar store, cafe, and counseling office
- Area beyond the wall will be classrooms and the media center (library)
North News:
-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/12
General News:
-
Project continues on schedule with similar work on foundations, masonry, mechanical rough-ins, steel work… many workers are on site