Notes: Administrative update of September 6

Posted by EDWARD POPRIK on 9/6/2016

South News:
  • Trailers work is continuing
    • A variety of tasks to be completed as well as code compliance and inspection are on order
    • Completion Target: the week of 9/19
  • Work closest to the South Library (if you haven’t been to the South library to take a look, it is worth your time)
    • Concrete retaining wall is for the main mechanical wall
    • On top of that wall will be the floor of the new gym (hard to believe)
    • Area to the right of that will be the student success lab, roar store, cafe, and counseling office
    • Area beyond the wall will be classrooms and the media center (library)

 

North News:
  • Trailers work is continuing
    • A variety of tasks to be completed as well as code compliance and inspection are on order
    • Completion Target: the week of 9/12

 

General News:
  • Project continues on schedule with similar work on foundations, masonry, mechanical rough-ins, steel work…  many workers are on site